List of references

R&D plants C.Zeiss

RMA
01.2021 - vor. 12.2025
Project planning and electrical construction of R&D plants
  • Creating M&C lists for pre-planning the plant projects
  • Implementation of new IO link components
  • Installation on site
  • Evaluation to Zeiss standard
  • Generation of P&I diagrams

Charging infrastructure

elexon Aachen
01.2022 - 10.2022
Project-planning and standardisation of distributor plans for charging infrastructure
  • Creation of circuit diagrams in series to customer requirements
  • To 09.2024 # 1200 pc. circuit diagrams

Process goals

ILT Fraunhofer Aachen
01.2022 – 01.2022
Project planning and construction of a process cell with a laser welding facility
  • Complete electrical construction of the circuit diagrams with Eplan-P8, incl. installation plans and material procurement
  • Constructing and testing a prototype control cabinet
  • Installation of process cell on site

Cross-cut plant

Pollmeier Schnittholz
Project planning and construction of a new hardwood cutting plant
  • Electrical construction of circuit diagrams with Eplan-P8 incl. layout plans and materials tracking
  • Material procurement & control cabinet construction
  • Installation of the electrical components on site
  • Initial commissioning and accompanying measurements of a control cabinet & plant

Run-around plant for hardwood

Pollmeier Schnittholz
Project planning and construction of a new hardwood run-around plant (resaw 4)
  • Taking on electrical construction of circuit diagrams with Eplan-P8 incl. layout plans and materials tracking
  • Determining material procurement requirements
  • Supervision at the customer’s site
  • Initial commissioning and accompanying measurements of a control cabinet & plant

ILT AC / DESY HH

ILT Fraunhofer
Test setup for long-term testing of laser welding processes
  • Planning and technical elucidation of all components
  • Consideration for various safety provisions
  • Site visit before installation of the plant on site
  • Construction of control cabinets and manufacture of connection cables

Conveyors

Kardex mlog
Retrofitting high-bay storage incl. transport system Grünenthal Aachen Retrofit P&G Gross Gerau
  • Recording the current state of installations on site
  • Technical elucidation on site
  • Conversion of the old control system to a fault-free, updated one
  • Conversion of safety control devices
  • Exchanging electrical vertical conveyor components incl. drive and measuring devices; feasibility checked on site.
  • Supervision and online revision of plans at the customer's premises

Process welding plant

ILT Fraunhofer Aachen
Project planning and construction of a prototype process welding plant for innovative welding processes
  • Complete electrical construction of the circuit diagrams with Eplan-P8, incl. installation plants and material procurement
  • Constructing and testing a prototype control cabinet
  • Integration of Data Matrix Barcode Scanner

High-bay storage retrofit

Kardex mlog
Project planning and retrofit of high-bay storage with automatic entry and removal
  • Conversion of circuit diagrams to new E-plan P8 system
  • Incorporation of customer wishes in the drawings
  • Comparison with new standards
  • Material tracking
  • Supervision and online revision of plans at the customer's premises

Treatment plant

Otto Junker Gmbh
Project planning and construction of a conveyor system
  • Complete electrical construction of the circuit diagrams with Eplan-P8, incl. installation plants and material procurement
  • Administering the MUK list
  • Material procurement
  • Electrical plan database administration

Laser bonding plant

ILT Fraunhofer Aachen
Project planning and construction of prototype control cabinets for mass production laser bonding machines
  • Complete electrical construction of the circuit diagrams with Eplan-P8, incl. installation plants and material procurement
  • Construction and testing of prototypes
  • Approval as per SEMI 2
  • Modular system introduced / serial number administration

Processing plant

Chiron GmbH
Wholesale re-planning of processing machines
  • Complete re-planning of a processing line in E-plan P8, incl. installation plans and material control
  • General conversion to E-plan P8
  • Administrative database work
  • Conversion and extension in agreement with specialists before assembly

Liquid metal plant

Otto Junker GmbH
Project-planning and construction of an aluminium recycling smelter (GARMCO REMELT BAHRAIN)
  • Complete electrical construction of the circuit diagrams with Eplan-P8, incl. installation plans and material control
  • Concurrent construction at the customer’s site
  • Preparation for I/O test
  • Supervision, conversion and extension on site

Palleting plant

Sonoco
Project planning and construction of a tubular sleeve palleting plant
  • Complete electrical construction of the circuit diagrams with Eplan-P8, incl. installation plans and material control
  • Concurrent construction at the customer’s site

Heat treatment plant

Hütte Thermoprozesstechnik
Project planning and construction of a heat treatment plant
  • Complete electrical construction of the circuit diagrams with Eplan-P8
  • Creation of parts lists
  • Calculating air conditioning requirements
  • Creating modular groups
  • Creating an installation plan with cable lengths
  • Risk evaluation & analysis

Filling plants

SIG Combibloc
Project planning and construction of prototype filling plants
  • Construction of circuit diagrams with Eplan-P8
  • Calculating the power supplies and main circuit breaker
  • Creation of installation plans with Eplan-P8
  • Ordering materials in SAP
  • Handling service orders in SAP
  • Creation of pneumatic and technological plans
  • Support/monitoring of mechanical and electrical structure of prototype plants

Packaging plants

PESTER PAC
Project planning and construction of packaging plants
  • Construction of circuit diagrams with Eplan-P8
  • Calculating the power supplies and main circuit breaker
  • Creation of installation plans with Eplan-P8
  • Ordering materials in SAP
  • Handling service orders in SAP

Energy management

Grünenthal GmbH
Installation & commissioning of energy and heat meters for energy management
  • Creation of overview drawings in Eplan-P8
  • Corresponding meter lists with addresses created in Excel
  • MS network recorded, overview layout created
  • Overview layout of low-voltage network W5 created
  • Commissioning of heat meters
  • Connection to building control systems

Heat treatment plants

BSN Thermprozesstechnik
Electrical construction of various heat treatment plants for the automotive industry
  • Creation of electrical documentation with Eplan-P8
  • Parts lists created in Excel
  • Electrical equipment transferred to plant layout
  • Layout plan (electrical) created for entire plant
  • Calculation of all power supplies
  • Calculation of power loss
  • Support for control cabinet construction
  • I/O test of control cabinet
  • Control cabinet signage
  • Plant signage
  • Cable route planning for the entire plant
  • Creation & delivery of customer-specific plant signage

Ventilation plants

AXALTA
Electrical documentation for an existing ventilation plant for various production buildings
  • Creating control cabinet layout plan
  • Creating a measurement point list using the programming lists and old documentation
  • Creating electrical documentation with E-plan P8
  • Creation & delivery of customer-specific plant signage

Tempering furnaces

Elektroanlagen Hensch
Electrical construction of two tempering furnaces
  • Creation of electrical documentation for the furnaces with Eplan-P8
  • Creating a measurement point list in Excel using the P&I diagram
  • Exporting parts lists for the customer in the desired format
  • Translation of documents into English

Electroplating plants

Kroes GmbH / Daimler
Electrical construction of an eloxal coating plant for Daimler Benz
  • complete construction of an eloxal plant with Eplan-P8

Semiconductor industry

Aixtron SE - Herzogenrath
Planning, project planning of several development plants in the field of LED/OLED manufacture
  • E-plan construction for the OVPD field
  • New planning concept drawn up for the creation of e-docs
  • Customer requirements included
  • Production documents for control cabinet manufacture and plant manufacture created using clean room technology
  • Certification and testing of new measurement systems for the clean room/vacuum technology
  • Change logs created for servicing
  • Electrical documentation drawn up in two languages (German/English)
  • MUK list introduced in planning preparation
  • Calculation of power loss, power & control circuits
  • Database created for electrical construction
  • Newly developed power electronics from various manufacturers certified

Electroplating plants

Aucos GmbH Aachen
Electrical construction of electroplating and eloxal plants
  • Creation of measurement point lists according to flow diagram
  • Concept creation of plant + local BMK labelling
  • Circuit diagrams incl. cable connection plan, order & parts list
  • Design plans created for control cabinet construction
  • Pre-commissioning at the customer’s site
  • Support for control cabinet construction at customer’s premises
  • Standardised/modular terminal boxes created
  • Calculation of power supplies
  • Cross-section calculation for emergency stop/load circuits
  • Cable standardisation
  • Drawing standard created

SMS Demag

Project planning and modularisation
  • Modularisation of a cooling line for a hot rolling mill
  • Project planning of crop shears
  • Calculation of cable aggregation for cable laying
  • Calculation of low-voltage power supplies
  • Power loss calculation of control cabinet components
  • Part project planning for NSHV

Grünenthal GmbH Aachen Werkteil 5

08.2005 – 2020 / aktuell
Creation of all control and distributor plans and circuit diagrams to customer desires in E-Plan
  • Creating a non-ambiguous structure in the circuit diagrams by plant and location; involvement of specific customer desires
  • Complete revision of all circuit diagrams for Werkteil 5
  • Changing various forms of circuit diagrams according to customer desires and needs
  • Creation of building control system station (ZLT) overviews with Auto-CAD; assignment of logical addresses
  • Creation of circuit diagram macros for the ZLT components
  • Construction of a solvent supply and disposal station to customer wishes

Grünenthal Aachen Werkteil 2

Creation of all control and distributor plans and circuit diagrams to customer desires in E-Plan
  • Revision of all control and circuit diagrams
  • Creation of an unambiguous structure in the circuit diagrams

Kesko GmbH (Packaging and filling industry)

Transfer of production to a new hall (electrical site management)
  • Division of production relocation into individual production stages
  • Machine installation plan created (Auto-CAD)
  • Planning and execution of electrical installation for production
Revisions
  • Revision of circuit diagrams for all production machinery with E-Plan
  • Creation of a revision management system
Automation of a packaging machine
  • Quantity recording of all 4 packaging lines
  • Creation of documentation and changes in the existing circuit diagram with E-Plan

Oberlin Filter GmbH Eschweiler

Specialist support for electrical construction
  • Construction of various filter plants with Eplan P8
  • Control cabinet construction & testing plants

PARSYTEC AG

Construction of a test system for surface inspection systems
  • Creating documentation with E-Plan
  • Electrical construction of an automatic positioning unit